Hi;
I have tests with transfer of employees.
I select all employees or one it´s the samme, the problem occurs also. When execute the phase Start data transfer, the system do until 95% por or less, ever hold in PA0023
If I see the jobs, I can see that the system is hold in job;
PA0023
The others job, PA0001, PA0003, etc has finish correctly. I can see process in the system running but the job never finish.
The last phase Transfer data no running beacuase wait to finish Start data transfer. In SE16 the table PA0023 have in sender system 1104 records but in target system 0.
Any Idea?
Best regards